Skip to main content

Manufacturing order

Status

  1. Created: MO created following manufacturing principles:
    1. Make to stock
    2. Make to order
    3. Configure to order
    4. Engineer to order
  2. Scheduled: Materials and resources estimated. The estimation generates inventory transactions for raw materials that have a status of On order. The receipts for main products, co-products, and by-products are generated when production orders or batch orders are estimated. MO have set dates
  3. Released: MO to be released into the shop floor. The material availability checked. Materials ready to be picked
  4. Started: Resource and material consumption starting. MO can't be rescheduled at this point.
  5. Completed: Quantity fulfilled.
  6. Closed: MO cancelled for different reasons.